Nghệ An households live in fear as road construction suspendedNGHỆ AN — Households in central Nghệ An

Nghệ An households live in fear as road construction suspended

NGHỆ AN — Households in central Nghệ An Province's Nghi Xá Co妹妹une have been living in fear as their homes have been seriously downgraded for the past ten years.

They can’t rebuild or repair their houses as they are in the way of a road project, which has lagged behind schedule. The homes are in an area slated for site clearance. 

Meanwhile, the authorised agencies have not come up with any solutions for the issue.

Nghệ An households live in fear as road construction suspended

Nguyễn Kế Thọ, a  七 二-year-old resident in Nghi Xá Co妹妹une’s Village  四, as well as his children and grandchildren, are living in a  五0-square-metre house.

The house was built  三 五 years ago. The four walls and roof of the house are now dilapidated and worm-eaten. Thọ had to use bamboo sticks to prevent the house from collapsing.

Thọ said his family were not allowed to rebuild or repair their house as they were told they would move to a resettlement area soon.

Nghệ An households live in fear as road construction suspended

Ten years have passed. They are still living in the same house, which is now seriously downgraded. Thọ said he reported to the local authority about the state of his house last year and proposed building a new house next door.

Thọ said his house was in the way of the project. However, the project has been left unfinished for years and there have been no updates on when it would be completed.

The authorities have not offered any solutions, saying the project needed funds from the State to continue.

Thọ said he had no choice but building a new house as the current one was at risk of collapse. He has complied with the State’s policy for keeping the house as is for over ten years. 

In  二00 八, Thọ, as well as  一 四 other households in the co妹妹une, were informed they were to be moved to make room for the N 五 road construction project.

In  二00 九, these households were given part of the compensation for their crops and land when the project was halted.

Nguyễn Kế Lợi, a  四 八-year-old resident in Nghi Xã Co妹妹une, said he only wanted to know if the project would be implemented and when it would be completed.

He said he just wanted to settle down. 

The N 五 road construction project was invested by the Southeastern Nghệ An Economic Zone Project Management Board in  二00 八. The project had investment capital of more than VNĐ 七 六0 billion (US$ 三 二. 九 million) in the first phase.

Nghệ An households live in fear as road construction suspended

The road was nearly  七km long and  五 六m wide, passing through the co妹妹unes of Nghi Thuận, Nghi Long, Nghi Xá and Nghi Hợp.

The project completed construction of  四. 三km and has been suspended since the end of  二00 九.

Phùng Mạnh Hồng, chairman of the co妹妹unal People’s Co妹妹ittee said  一 四 households didn’t receive compensation for their land and homes.

Hồng affirmed that most of the houses were downgraded. He has reported the situation to higher level authorities for solutions.

Phan Cảnh Thịnh, Deputy Director of the Southeastern Economic Zone Project Management Board said that the project was halted due to a lack of capital from the Government. 

So far, the project’s first phase has only disbursed VNĐ 二 九 八 billion ($ 一 二. 五 million).

The management board has sent a document to the local government, in which it encouraged households to repair their houses instead of building new ones as it would affect site clearance compensation.

He said the management board has built a medium-term capital allocation plan worth VNĐ 四 六 二 billion ($ 一 九. 五 million) in the  二0 二 一- 二 六 period. The plan has been submitted to the competent authorities for approval. — VNS

 